TRAVELLING LUFF AND SLEW STACKER FOR TKISSA AT EXXARO GROOTEGELUK


Exxaro Grootegeluk mine needed to increase their export coal capacity in order to meet the demands of the almost completed Medupi power station. They opted for an additional stacker to increase the stockpile capacity for export coal.

ThyssenKrupp Industrial Solutions won the tender to supply a Travelling, Luffing and Slewing stacker to Exxaro for the stockpile expansion. Because of the vast experience with bulk material handling machines and recently successful completion of a waste spreader at Exxaro, Hamar Controls secured the E&I installation contract from ThyssenKrupp Industrial Solutions which also included commissioning assistance.

Project Details


  • Started: June 2018
  • Completed: July 2019
  • Location: Lephalale, Limpopo Province, South Africa
  • Details: 1 Travelling Luff and Slew Stacker, weight 340t, 394m of travelling until midpoint, 2500t/h, MV, LV, Network installation, 10 travel drives, 2 slew drives